levee wall and green grass by sidewalk

Hart Park and Western Milwaukee Levee System Accreditation Projects 

Project Update

Thank you to all who attended the open house on June 11th at the Hart Park Muellner Building. The levee and floodwall improvements are planned for 2026 and 2027. These improvements include raising the levee along River Parkway and 63rd Street, raising the floodwall along Hart Park Lane, several storm sewer improvements, and tree removal near the levee to meet FEMA standards. The planned work areas are shown in this map.

As part of these improvements, MMSD is partnering with the City of Wauwatosa, which provided additional funding to improve a MMSD levee maintenance drive, which will create nearly 2,000 feet of recreational trail near River Parkway and 63rd Street.

The 2026/27 work is the first of several MMSD projects to maintain and improve the Hart Park and Western Milwaukee Levee System. Use the forms below to sign up for project updates or to submit a question or comment.

MMSD reviewed the entire levee system and identified improvements required for the system to be accredited FEMA. Improvements include adding additional height to levees and floodwalls at several locations, storm sewer improvements, and sewer rehabilitation.

Project Overview

For FEMA to recognize the completed levee system's flood risk reduction benefits requires a levee system accreditation application to FEMA for the entire Menomonee River levee system. Once FEMA approves a levee system application, remapping the floodplain in the surrounding project area can proceed.

The FEMA review process is expected to take up to three years. Some structures will remain in the mapped floodplain after the levee system is completed. These structures remaining in the floodplain will be evaluated for other flood risk reduction approaches, such as voluntary floodproofing and voluntary acquisition.

Ahead of the levee system accreditation submittal to FEMA, MMSD has reviewed FEMA standards for the entire system and has identified several improvements to the system that are required for the system to be accredited.

  • slide
  • slide
  • slide
  • slide

The levee system improvements are needed for the following reasons:

  • River flood levels have been updated since the original Hart Park Levee Project.
  • Projects downstream of Hart Park were implemented differently than the original design assumptions causing changes in flood elevations.
  • FEMA expectations and standards for levee systems have changed after high-profile levee failures since the Hart Park levee system design was completed.
  • Improvements have been identified for pipes crossing or near the levee where pipe inspections indicated pipe rehabilitation is needed.
  • Clarifications of FEMA standards for storm sewers have identified the need for new pipe closure capability for floods higher than the design flood.

Planned Improvements for the Levee System include:

  • Levee/floodwall improvements: Several locations have been identified where additional height or freeboard is needed to meet FEMA and WI DNR standards.
  • Storm sewer improvements: Several storm sewer systems have been identified where pipes will have closures added or will extend further downstream so that closures do not have to be installed.
  • Sewer rehabilitations: inspections of pipes crossing or near the levee system have identified deteriorated conditions that will be repaired.

Project Benefits

  • Reduce flood risk on an estimated sixty-two structures
  • Reduce flood insurance costs

 

Project Timelines

Levee and Floodwall Improvements

Spring 2021 – 2025 – Design

2026 - 2027 – Construction

Storm Sewer Improvements

2025 - 2027 – Design

2027 - 2028 – Construction

Pipe Rehabilitation

2025 - 2027 – Design

2027 - 2028 – Construction

Stay Informed

Comment / Question

*
*
*