drone image of western milwaukee river restoration

Western Milwaukee Phase 2B

Project Update

Project Nears Completion! 

As we begin the final work to complete the project, the partial road closure between N. Alois Street and N. Hawley Road will be reinstated. During this last phase of State Street construction: 

  • All businesses will remain open during construction. 
  • Eastbound State Street traffic will be directed to the detour route while westbound traffic will remain open. 
  • For the benefit of the local businesses, two-way traffic will be preserved west of the hard closure at 5120 W. State Street. 
  • Please use caution when driving through this area and promote responsible driving by following construction zone signs.

The project team thanks residents and businesses for their patience and understanding during construction. 

This project will extend the earthen levee system 1,800 feet eastward to reduce flooding along State Street, build a new 1,200-foot-long floodwall, install four new storm sewers, and restore 1,500 feet of banks along the Menomonee River.

Project Overview

The Milwaukee Metropolitan Sewerage District (MMSD) is partnering with the City of Milwaukee and City of Wauwatosa to make flood risk reduction improvements along the Menomonee River in Western Milwaukee along West State Street between North 60 Street and USH 175.

This project is part of the larger Menomonee River Watercourse Management Plan which aims to reduce the risk of flooding for over 300 homes and businesses. To see the existing floodplain map visit FEMA’s Flood Map Service Center.

The Western Milwaukee Phase 2B Project will:

  • Extend the earthen levee (a compacted soil embankment that holds back floodwaters during heavy rains) 1,900 feet, with a sloped soil embankment up to 8 feet high, to reduce flood risk from the Menomonee River flooding onto State Street during heavy rains from approximately 60th Street and West State Street east to US Highway 175. See bottom of page for example image.
  • Build a 1,200 foot long floodwall (a wall made of concrete that holds back floodwaters during heavy rains) training in a height of 5 to 10 feet on the landward side and up to 20 feet on the river side.
  • Install four new storm sewers totaling 5,100 feet.
  • 1,500 feet of excavation and bank restoration between the north and south banks of the river.
  • Turf and native plantings.

Project Area Photos

  • slide

    Widening the river channel below Doyne Park. 

  • slide

    MMSD Consultant working on removing material from the river along the south bank.

  • slide

    Loading trucks with top 6 feet of material at south bank.

Project Map

To recognize the levee system's flood risk reduction benefits, there will be a levee system accreditation application to the Federal Emergency Management Agency (FEMA) for the entire Menomonee River levee system (shown in the map above) and a remapping of the floodplain in the surrounding project area following completion of the project and completion of other FEMA-required levee accreditation improvements. FEMA review is expected to take up to three years. There are some structures that will remain in the mapped floodplain after the levee system is completed. These structures remaining in the floodplain will be evaluated for other flood risk reduction approaches, such as voluntary floodproofing and voluntary acquisition.

Project Benefits:

  • Help To Reduce Flood Risk
  • Increased Public Safety
  • Improved Riparian (area adjacent to the river) & Aquatic Habitat

Project Timeline:

2017 - 2023 Finalize Design

2023 - 2026 Construction

*Project timeline is subject to change

Project Status:

MMSD is completing construction.

Partner List:

Levee and Floodwall Rendering

rendering of western milwaukee phase 2b

 

Comments / Questions

*
*
*